Sorlandet

callsign LDTY flag Norwegian

Overhaul of rigging winter 2006 – 2007

  • Client Stiftelsen Fullriggeren Sorlandet
  • Main Contractor for rigging Mennens Amsterdam BV Finance, material purchase, logistics, personel
  • Subcontractor Richard Tefsen Sailmaster Project Management, on site implementation, personel
  • Subcontractor Stiftelsen Fullriggeren Sorlandet Personel from ships crew
  • Duration of project Oktober 8 2006 – April 12th 2007
  • Location Bredalsholmen Shipyard Kristiansand Norway

Project description:

  • Complete overhaul of rigging
  • Dismanteling and removing from the ship of fifteen yards, including sails and all running rigging
  • Disasembly and removal from the ship of Fore lowermast, fore topmast and foretopgallant mast and mainlowermast, maintopmast and main topgallant mast. Mizzenmast, Mizzentopmast, Mizzen topgallant mast and bowsprit.
  • Production of new standing rigging
  • Installation and assembly of masts, spars and bowspritwith new standing rigging
  • Installation of yards with sails and new running rigging.